Conon Avenue Bearsden Sewer Upgrade
Project Overview
We are delivering a project to upgrade the sewer network in Bearsden, ensuring that we can continue to deliver resilient waste water services for our customers in this area.
Our delivery partner George Leslie will be replacing a total of 143 metres of sewer in two separate locations across from Conon Avenue.
Works will commence on Monday 26th August, with preparatory works taking approximately 3 weeks, before the main works begin which will take approximately 7 months.
At a Glance
- Sewer network upgrades in Bearsden, Glasgow
- Work will start on Monday 26th August 2024
- Approx. completion: Spring 2025
- Delivered by: George Leslie
Bearsden Sewer Upgrade
We are upgrading the sewer network next to Conon Avenue in Bearsden, Glasgow.
What We Are Doing
On Monday 26th August we will begin with preparatory works for approximately 3 weeks. No traffic management will be in place during this time and access to properties and footpaths will be maintained.
Following this, we will be replacing an 80 metre section of the sewer within the parkland adjacent to Conon Avenue/Annan Drive.
To accomplish this, we will carry out permeation grouting to reduce water ingress prior to installing sheet piles to enable us to build two new chambers.
Sheets will be installed one-by-one, using a hydraulic press (a vibration-less system) to carefully push them into the ground. The decision was taken to use this method to minimise noise and vibration as much as possible.
Following this, a specialised moling machine, designed for laying pipes, will be employed. This technology enables us to install new sewers without having to excavate the ground between the chambers.
A 63 metre section of sewer adjacent to Conon Avenue/Teith Drive will also be replaced during this project.
Information Event Documents
View the posters from our drop-in community event that was held on Tuesday 30th July 2024.